Project Plan

 By: Sandra Paluszka

 

Item #

 

Deliverable or Action Item

Start Date

Due Date

Responsible Person

Status or Comments

1.0

 

Project Preparation

March 3

March 28

 

%100

 

1.1

Review Conference Project

March 3

March 7

All

%100

 

1.2

Job Application

March 3

March 7

All

%100

 

1.3

Cover Letter and Article Review

March 18

March 21

All

%100

 

1.4

Interviews

March 18

March 21

All

%100

 

1.5

Individual Proposals

March 18

March 21

All

%100

 

 

 

 

 

 

 

2.0

 

Project Plan

March 31

May 22

 

100%

 

2.1

Individual Project Plans

April 2

April 8

All

100%

 

2.2

WS Plans and Conference Plan

April 9

April 17

PM & PD

100%

 

2.3

Final WS and Conference Plan

April 9

April 25

PM & PD

100%

 

 

 

 

 

 

 

3.0

 

Workshop and Conference Proposals

April 7

April 25

 

100%

 

3.1

Finalize Workshop Topic & Software

April 7

April 11

All & CIO

100%

 

3.2

Update Wiki with Individual Reports

April 14

April 17

All

100%

 

3.3

Workshop Team Meeting & MOM

April 24

April 24

All

100%

 

3.4

Create & Submit MOM Reports

April 14

April 25

PM & MM

100%

 

3.5

Submit Risk Analysis & Agenda

April 14

April 25

PM

100%

 

3.6

Submit Marketing Plan, Logo, & Material

April 9

April 25

MM + CMO

100%

 

3.7

Submit Final Conference Schedule

April 22

April 25

PM

100%

 

3.8

Submit Final Workshop Descriptions & Duty Roster

April 22

April 25

WM

100%

 

3.9

Submit Business Application Summary & Tips Handout

April 22

April 25

TLM

100%

4.0

 

Presentation Preparation

April 22

May 16

 

100%

 

4.1

Create Workshop and Conference Presentation & Notes

April 22

May 5

PM, WM, MM

100%

 

4.2

Create Workshop Promotional Video

April 22

April 25

TLM

0%

 

4.3

Workshop Team Meeting & MOM

May 1

May 1

All

100%

 

4.4

Submit Workshop Promotional Video, Workshop & Conference Presentation & Notes

April 28

May 5

MM, TLM, CIO & CMO

100%

 

4.5

Workshop Team Wiki Page

April 2

May 2

All

100%

 

4.6

Submit Peer Performance Evaluation

April 28

May 2

All

100%

 

4.7

Submit Recommendations to improve Team Organizational Culture

April 28

May 2

All

100%

 

4.8

Workshop Team Meeting & MOM

May 8

May 8

All

100%

 

4.9

Rehearse Conference – Presentations and Workshops to Class

May 5

May 9

All

100%

 

4.10

Submit Peer Presentation Checkbrick Assessments

May 5

May 9

All

100%

 

4.11

Workshop Team Meeting & MOM

May 15

May 15

All

100%

 

4.12

Rehearse in Auditorium

May 12

May 16

All

100%

 

4.13

Team Meeting – Submit Agenda & MOM

May 12

May 16

PM

100%

 

 

 

 

 

 

 

5.0

 

Conference

May 20

May 23

 

0%

 

5.1

Workshop Team Meeting & MOM

May 22

May 22

All

0%

 

5.2

Final Reminders to Teachers

May 20

May 23

All

0%

 

5.3

Complete Workshop

May 20

May 23

All

0%

 

 

 

 

 

 

 

6.0

 

Conference Debrief

May 26

May 30

 

 

 

6.1

Team Debrief with Mr. Gill

May 26

May 30

All

0%

 

 

Risk Analysis

There are a few risks that our group may encounter. The first risk is some group members not completing their work on time or at all. If this happens, the WM and/or PM will discuss it with them and see if they need assistance or help with the task. Another approach we may take, if it happens constantly, is talk to the Executive team or if necessary, Mr. Gill.

The next risk we may encounter is technology not working when we are to present. This is why we will make sure to have a rehearsal and make sure that everything is running smoothly on the school computers. In case the Internet is not working at school, we will be sure to have everything we need on a USB stick.

Lack of communication or motivation is another risk that is bound to come up. Having team meetings and discussing issues at hand as well as possible solutions should help work this out. This will allow the team to work to its fullest potential and deliver a great workshop at the conference.

Time management is of essence in this type of project. To keep the group on track and aware of due dates, the project plan has been posted on the Wiki so that it is easily accessible. Also, good communication between team-members will allow everyone to help each other out, keep on track (time-wise), and have great motivation.

 

Comments (5)

chris gill said

at 1:02 pm on Apr 20, 2014

Hi, It looks like you updated some items from the original version which is good and remember to update a final version for April 25. You should have update risks for this version. Your section 2 on the project plan should continue to May 22. You should add the following more detailed items. Scheduled workshop team meetings and MOM, updated risk analysis, all team to add April 17 Proposal material to Wiki and status. Similarly April 25. New risks may come up or may be solved. Perhaps you can have a different heading under each Risk that you are managing? You team should now be giving you more details and issues on their deliverable.

Sandra said

at 8:30 pm on Apr 22, 2014

Hi Mr. Gill,
I have made the changes you've suggested and added additional risks.

Prashanthi said

at 2:40 am on Apr 25, 2014

I like how you have updated your project plan with all the tasks that have been completed. Continue to do this throughout the project!

Sandra said

at 9:43 pm on May 5, 2014

Thanks Prashanthi!

chris gill said

at 9:35 am on May 7, 2014

I think at this rate all PM's should have a Key Things to do list on their Main Team page and use the Conference Calendar that Prashanti has. Also look at the course schedule on the class website.